Safety Culture
OHS Systems Work Method
Statements
Safety
Training
OHS Audits Safety Shop OHS News

Procedures
1
1 Safe Work Procedures
1
1
1
1 Commercial Construction Industry
1
Site Plan Concrete Safety
1
Site Plan Earth Moving Procedures
1
Site Plan Industrial Safety Procedures
1
. Transport Industry
1
. Plumbing Safety
1
. Painting Safety
1
. Steel Work Industry
1
. Custom Procedures
1
1 Garden Contractors
1
  Food and Kitchen Safety
1
OHS OHS Policies
1
1 Online Inductions
1
1 OHS System
1
OHS OHS Diary
1
OHS First Aid Kits
1

Asbestos Removal Safe Work Procedure or Work Method Statement

Asbestos Removal is extremely dangerous and this four page Safe Work Procedure or Work Method Statement is a vital part of a safe work system.

The Safe Work Procedure Includes:

  • Site Awareness
  • Personal Protective Equipment(PPE)
  • Pre-Start Checks
  • Asbestos Sheets
  • Friable Asbestos
  • Decontamination
  • Disposal
  • And more
  • 4 Page Complete Procedure
  • MS Word Format
  • Ready to Use
  • Version 4.0

 

SWP_Sample

 

Back      Buy Now $79.95 ex GST

Asbestos Removal Safety Notes

Before Removing

Consider the following:

  • Was the building built before 1990?
  • Is the surface of fibro construction?                     
  • Is there any friable asbestos behind the surface?

When Removing Asbestos Always

Asbestos_Firable

Ensure that;

  • Power tools are not to be used for cutting or drilling sheets.
  • Use a nail punch to punch all nails through the sheets and into the timber.
  • Use a large punch to cut a hole around screws.
  • Prise sheets away from timber framing using a pinch-bar or similar.Keep sheets intact where possible.
  • Unnecessary breaking of asbestos-cement sheeting must not be permitted.

Asbestos_Safety

 

General Asbestos Safety Continued

  • Asbestos waste should be collected in heavy-duty 200 μm (minimum thickness) polythene bags that are no more than 1200 mm long and 900 mm wide.
  • Only previously unused bags should be used.
    NOTE - Bags marked for asbestos waste should not be used for any other purpose.
  • Bags to be labelled with a warning, clearly stating that they contain asbestos and that dust creation and inhalation should be avoided.
  • An example of a warning statement which might be used is:
    CAUTION – ASBESTOS - DO NOT DAMAGE OR OPEN BAG - DO NOT INHALE DUST - CANCER AND LUNG DISEASE HAZARD


CLICK HERE - Safe Work Procedure - NSW ASBESTOS REMOVAL

For Asbestos Removal Procedures Specific To NSW Legislation From July 1 2007 Click Here

For Asbestos Removal Procedures For Victoria Click Here

For All Other States, A Complete Asbestos Removal Safe Work Procedure By Choosing The By Now Option Below.

Back      Buy Now $79.95 ex GST


 

OHS Systems

OHS System - General
Construction OHS
OHS System Audit
Transport Safety
OHS Diary
OHS Equipment Registers
Safety Maintenance Log
Incident Report Forms
Construction Site Sole Trader
Industrial Sole Trader Pack
Work Method Statements (WMS)

Construction WMS
Residential Construction
Engineering WMS
General Safe Work Procedures
Earthmoving WMS
Custom Safe WMS
Complete WMS List
How to develop a WMS
Safety Training

Online OHS Induction Courses
Safety DVD's
OHS Consultants
Safety Induction
OHS News
OHS Auditing

On Site OHS Audits
OHS Consulting
Safety Audit
Equipment Safety Audit
Construction Site Audits
First Aid Kits

Portable First Aid Kits
Softpack First Aid Kits
Wallmounted First Aid Kits
High Risk Risk First Aid Kits
Mining Industry First Aid Kits
Construction First Aid Kits
National First Aid Kits