The Safety Procedure includes:
- PPE
- Safety Notes
- Planning
- Preparation
- Pre-operational Inspection
- Operation
- Maintenance
- Emergency Procedures
- References
Product Details:
- 20 Page procedure
- Written by ex WHS inspectors
- Referenced
- Risk ratings before and after control measures
- MS Word format NOT PDF
- Task specific and site specific details easy to add
- Includes easy to complete boxes for Company details and project details
- Employee sign off section
-
Instant download delivery
Related Items:
|
Roof Tiling Information:
The Roof Tiling Safe Work Method Statement (SWMS) is a comprehensive 20 page procedure. This SWMS covers general safety aspects associated with roof tile installation. It does not contain detailed information in relation to plant and equipment (such as Truck mounted cranes, Forklifts, Tile/Block Elevators, Ladders, Scaffolding, Power grinders, etc) as these require a dedicated SWMS.
The Roof Tiling procedure is ready to use and is not a blank template. Simply add your company details, ABN, and include any site specific details or risks and make it specific to the task at hand. It is then ready for printing and to be incorporated as part of your overall OHS System.
The Roof Tiling Work Method Statement can be used as part of your OHS inductions, for Tool box talks or tender applications.
Planning:
Inspect roof. Ensure safe for work. Check:
- Certification from structural engineer (if possible)
- Rafters braced adequately
- Creeper rafters secured
- Valley irons supported
- Truss and Batten erection:
- Where no internal fall protection provided:
- Truss spacing must not exceed 600mm centres
- Batten spacing must not exceed 900mm centres
- Where truss spacing is more than 600mm but less that 900mm, batten space must not exceed 450mm centres.
- If truss exceeds 900mm and batten spacing exceeds 450mm then suitable fall protection MUST be provided.
Condition of trusses, rafters, purlins and roof battens
Presence of cement sheeting
Brittle roof surface, asbestos, skylights or other hazards
Check strength of installed safety mesh. Check:
- Corrosion
- Fixed correctly
- Provide temporary props if needed
Clear of overhead power lines
Incomplete areas
Acceptable pitch
|